Hearing Updates

Home

WE NEED YOUR FINANCIAL HELP!

PLEASE MAKE YOUR CHECK PAYABLE TO:

WCRE

 

AND MAIL IT TO:

THE WOODLANDS COALITION

657 Hurst Road

Palm Bay, Florida 32907

 

Contact Us
Hearing Updates
Coalition Information
Hartford News
Washington Updates
Event Calendar

 

 

It is the intent of the Woodlands Coalition to provide here brief synopsis of each days hearings. we will have the updates in place by 9 PM each evening. Please keep in mind that this process is, if nothing else, a roller coaster. Each day is different, with its own successes and setbacks. How things are going can change moment to moment.  We hope that you will be able to come to a day or 2 of the hearings, even if it is only for a brief stay. It is the best way to really understand the process and its outcomes. We also understand it isn't easy to get to New Britain and that is why we provide these updates.

 

As you know, the Connecticut Siting Council rendered their decision on April 7, 2005 on Docket 273, the proposed transmission upgrade for a 345kV line from Middletown to Norwalk. We are now in the D&M phase or the Design and Management Phase, where the actual line is being designed.

 

There are many steps that will be taken before the construction for this line will actually begin. You will find on this page "next steps". Pasted below is the procedures that will take place with ISO-NE. We thank ISO for providing this information to us in concise terms. 

PPPPPP

  • Reliability Design Determination

      Connecticut Light & Power and United Illuminating (“Utilities”) must file what is referred to as an I.3.9 Application.[1]  Under Section I.3.9 of the ISO Tariff, any Transmission Owner must notify the ISO of its plan to install any transmission facility that is greater than 69kV. 

     This application is for what is informally referred to as the reliability design determination.  Generally, the ISO has 60-90 days to make its determination after the Transmission Owner files its application.  The ISO makes its determination after receiving the advisory input of the NEPOOL Reliability Committee.               

     The purpose of this notification is to the provide the ISO with information to allow the ISO to determine whether the project will have a “significant adverse effect upon the reliability or operating characteristics of the Transmission Owner’s transmission facilities, the transmission facilities of another Transmission Owner, or the system of a Market Participant, the Market Participant or Transmission Owner.”                             

     Until the ISO makes that determination, the Utilities may not take any significant action (other than preliminary engineering action) to install the transmission facility.                    

     If the ISO determines that the project will have such a significant adverse effect, then the Transmission Owner shall not proceed to implement the project unless the Transmission Owner takes such action or constructs at its expense such facilities as the ISO determines to be reasonably necessary to avoid such adverse effect.

  • Regional Cost Allocation 

After receiving a determination that a proposed transmission project will have no significant adverse effect, the Transmission Owner may obtain a decision from the ISO under Section II, Schedule 12C[2] of the ISO tariff to include the costs of the transmission project into the regional transmission service rates.  The ISO makes its determination after receiving the advisory input of the NEPOOL Reliability Committee. 

The NEPOOL Reliability Committee, and the ISO, may ask the Transmission Owner for additional information to assist them in making the determination.  Typically, the NEPOOL Reliability Committee will meet 1-2 times for simple projects, and can meet more than three times for complex and large additions of transmission facilities.  There is no deadline by which the NEPOOL Reliability Committee must provide its advisory input, and the process can take several months to complete  

The Schedule 12C Application provides the details of the costs of the project, and the Transmission Owner must identify any significant additional proposed regionally supported costs that are introduced as a result of local or state regulatory and/or legislative requirements.  In reviewing the Application, the NEPOOL Reliability Committee may advise, and the ISO may decide, that certain of the costs should be excluded from regional transmission service rates. 

      Excluded costs are referred to as “Localized Costs” under the ISO Tariff, and are those costs which exceed those requirements that the ISO deems to be reasonable and consistent with Good Utility Practice and the current engineering design and construction practices in the area in which the Transmission Upgrade is built.  In making the determination of whether Localized Costs exist, the ISO will consider the reasonableness of the proposed engineering design and construction method with respect to alternate feasible Transmission Upgrades and the relative costs, operation, timing of implementation, efficiency and reliability of the proposed Transmission Upgrade.


[1] This used to be referred to as the “Section 18.4 Application,” which referred to the Section of the Restated NEPOOL Agreement that applied.  With ISO-NE’s commencement of RTO operations on February 1, 2005, the provisions of Section 18.4 of the Restated NEPOOL Agreement were transferred to Section I.3.9 of the ISO New England Transmission, Markets and Services Tariff, which is available at: 

http://www.iso-ne.com/FERC/filings/tariff/

PPPPPP

 

April 7, 2005

Connecticut Siting Council Meeting

Today, the Siting Council voted 9-0 to certify the proposal by Northeast Utilities and United Illuminating to upgrade the transmission lines: 345kV from Middletown to Norwalk.

 

For all of the4 details of that certification you may go to the following link:

 

Connecticut Siting Council Certification of Docket 272

 

April 5, 2005

Connecticut Siting Council Meeting                                                                            Today the Siting Council reviewed the revisions to its Findings of Fact, and then its draft Decision and Opinion. The Chair put some test questions to the members as a straw vote to gauge opinion on some matters still unresolved in the opinion. Consensus has already gathered around 24 miles underground from East Devon to Norwalk. Now, consensus is gathering around the ROW as a buffer zone; prudent avoidance to reduce mG levels per designs offered by the applicants; a chance for the towns to suggest preferences on tower heights and other variables before the Council during the D&M phase; and the following local actions: a) the bypass option around Royal Oaks; b) at the JCC in Woodbridge, the proposed route—no change; c) at Ezra Academy in Woodbridge, a “jog” on the existing ROW, no bypass to nearby property. However, this report is provisional only. Some Council members were not present for the straw vote, and others wanted to discuss each matter further. 

PPPPPP

  1. Review of draft. The Council reviewed the general background points in the draft opinion, and new points of law which have been added. They generally assented to these parts of the draft, which provide justification for their decision, rather than specifying points of decision.
  1. Prudent Avoidance.” The test statement here was, roughly, “Based on previous discussions, the Siting Council does not think it is possible to set a specific mG level as ‘safe.’ We embrace the concept of ‘prudent avoidance’, to mean ‘reduce where possible.’” This statement was generally accepted.
  1. ROW and Second-Level Prudent Avoidance Designs. The test statement here was that the starting point for prudent avoidance to mG levels will be the second-level designs outlined by the applicant in the relevant tables. Various options are outlined in this table to accomplish reductions. There was considerable discussion on this matter, with members disagreeing on the starting point for the reductions. This will need further conference on Thursday.
  1. Town comments. The test statement here was roughly as follows: if any towns want to take prudent avoidance one step further, and have even taller towers, or pursue other options to reduce mG levels per their own choices, they can do so at the D&M phase. A process already exists for the towns to have input to the D&M phase, so they may take advantage of that re prudent avoidance. All comments should come through the CEO, and towns must meet the regular 30-day response deadline. Towns in the East Devon to Norwalk part of the route may want to address mG concerns as well as towns from East Devon to Middletown. There was some disagreement on this statement, as some members felt the Council should make the difficult decisions on the towns’ behalf, especially since most towns have made their wishes known already. Other members felt that the towns have been given assurances that they could have further input, that the process for input already exists, and that the towns may not have been able to focus on specific variables before a basic decision was rendered.
  1. Local options. The following test statements were made—

Royal Oaks: Leave the 115kVs where they are now, and put the new 345kV lines onto the supported bypass.                                                                                 JCC: no change.

Ezra Academy: move the line to reduce mG levels on the present.              There was no disagreement on any of these points.

  1. Next steps. On  Thursday, the Council will receive a new draft opinion per their comments today, will review it further, and will vote on the final decision and opinion.

 

March 31, 2005

Connecticut Siting Council Meeting

Today, the Siting Council heard oral arguments from all Parties and Intervenors in Docket 272. Since time was limited, Siting Council Chairman Pam Katz asked all speakers to address only major points or issues regarded as particularly unclear or controversial. Following the mostly brief presentations, Council

 

PPPPPP

 

 

1.Applicants. Attorneys for the Applicants dealt mostly with underground technology; EMF, especially the meaning of “prudent avoidance”; and a request for construction guidelines to be used in negotiations with DOT. A variety of questions were asked on these issues. Answering one added question about the applicability of PA 04-246  to Docket 272, the attorneys said the Applicants don’t intend to claim the PA 04-246 is unconstitutional.

 

2. Attorney General. The Attorney General argued for setting “safe” standards to protect public health, with Department of Public Health to be used as the authority. He suggested that the public should be involved in the D&M phase of Docket 272 following the April 7 decision, perhaps through special public hearings, perhaps through elected officials; he said condemnation of properties might be an “available” remedy to satisfy a buffer extending beyond the ROW, even though a last resort; he thought costs should not be an issue, as he expects costs to be regionalized; he acknowledged that a buffer might be required for underground as well as overhead installation; and, pointing out that today’s questions showed the Council’s decision is still “a work in progress”, he suggested the Council could delay its decision past April 7 to “get it right.”

 

3A.Municipalities, General Points. Several municipalities’ attorneys appeared as a group, first giving general arguments they’d agreed upon and previously written in their briefs. Their general arguments were that: 1) more of the line should be put underground—this will be possible through technological innovation ; 2) where the line can’t be put underground, a buffer zone should be established at 3 mG; 3) the line loadings used to calculate mG levels are unreasonable; 4) the establishment of buffer zones can’t result in any property condemnations; 5) buffer zones should be applied to underground portions of the route as well as overhead; 6) the Council’s BMPs, especially not the ones improperly upgraded in 2004, but even the ones written in 1993, are not adequate to protect public health and safety; 7) related to deficiencies in the BMPs,(best management practices) the companies have not complied with the Act; 8) because of the BMP deficiencies and other points, the Council does not have the authority to certificate Docket 272.

 

3B. Municipalities, Particular Points. Each of the municipality’s lawyers went on to address particular needs.

[Milford]: a) Only 3.5 miles of undergrounding would be necessary to protect Milford, and so far no one knows that this isn’t possible, as no one has studied it; b) Milford’s issues haven’t been given due consideration by the Council.

[Woodbridge]: a) C-filters can be used to achieve more undergrounding [this argument included a review of KEMA’s change in position]; b) applicant has admitted a “porpoise” could be constructed through Woodbridge; c) the same standard of protection can’t be used for all municipalities, so large congregations of children should be given precedence, thus institutions in Woodbridge.

[Cheshire]: a) Old Farms residential district in Cheshire is the classic sort of case meant to be protected by the Act, therefore the supported change here is welcome, but more can be done, since b) applicant hasn’t shown further undergrounding is infeasible; c) the Act doesn’t authorize takings in connection with buffers.

[Durham-Wallingford]: a) Docket 217 should be re-opened so as to allocate appropriate underground mileage to Docket 272; b) build the supported bypass around the Royal Oaks neighborhood, and put both the 115 kV lines and the 345 kV lines into it.

[Middletown]: Supports Durham-Wallingford re the bypass.

[Middlefield]: a) congratulates Council on not preferring the northerly bypass; b) supports the Royal Oak bypass, but gives some history about the 3 towns’ agreement on the matter; c) urges no prohibitions on activities in the ROW, per Lyman Orchards golf course; d) points out that the undergrounding is being proposed for the system where it is weakest (Fairfield County), as opposed to where it is strongest (New Haven and Middlesex counties).

[Meriden]: Supports other municipalities.

[Westport]: a) Supports proposed route; b) supports a mG buffer for underground portions of the line.

[Orange]: a) Supports a 6 mG buffer recommended by DPH, with a balancing test done for 3-6 mG during the D&M phase; b) buffers can’t result in takings; c) wherever a buffer gets set outside of the ROW, the consequences are up to local zoning boards.

 

4. Further matter. During the Q & A after the munis’ attorneys spoke, a question came up about a meeting that had taken place between Woodbridge officials and the head of the CT DEP, Gina McCarthy. Few facts were available for the onlookers to understand this matter.

 

5. Debate with munis. As has been mentioned, the Council put a number of questions to the munis’ attorneys. The central issue seemed to be how much flexibility the Council might have in setting up buffer zones, or in enforcing restrictions on homes nearby or in buffer zones exceeding the ROW: the attorneys argued “very little”, based on the Act. On one new point, the munis agreed that public health considerations should be put above aesthetic ones (the visibility of high poles), though Orange’s advocacy for a different EMF standard in many places allowed for shorter poles. The Durham-Wallingford attorney reminded the Council about the environmental consequences of high poles.

 

6. OCC. The Office of Consumer Counsel argued for Alternative A, the 13-mile proposal, on the basis of its greater reliability. He also mentioned that least-cost, resource-neutral planning should have been done prior to the Docket, but came back, in the end, to the idea that a conservative approach to Docket 272, in terms of reliability, now is necessary.

 

7. DOT. The DOT attorney responded to the UI attorney (see above #1) on detailed points. At the end of the discussion, the Council had heard assurances that parts of the agreement for Docket 217 could be applied to Docket 272.

 

8. ISO-New England. ISO expressed its primary concern with reliability.

 

9. PSE&G. PSE&G supported the relocation of the proposed new Singer Substation in Bridgeport.

 

10. Royal Oaks Neighborhood. A resident of Royal Oaks spoke about the character of the 100-family neighborhood, residents’ fear of more than 3mG exposure, and their support for a bypass holding both the 115kV and 345kV lines. Questions from the Council focused on existing and proposed EMF levels.

 

11. Owners of Property Included in Proposed Royal Oaks Bypass. An attorney expressed the opposition of these property owners to the proposed Royal Oaks Bypass. He also addressed other issues mentioned by his fellow attorneys, such as EMFs, re-opening Docket 217, and the definition of “residential areas”—sometimes agreeing with his colleagues, sometimes not. He advocated adherence to the Act through use of a (trenched) gas-insulated transmission line, in some locations.

 

12. Woodbridge Educational Organizations. The attorney for this group presented the reasons for 2 proposed local re-routings in Woodbridge, and was questioned about them. He also argued in favor of more undergrounding in general, doubting the companies’ and ISO’s argument of unreliability.

13. Applicants’ Rebuttal. The first attorney to speak dealt with details of the 3 local bypasses proposed (Royal Oaks, and 2 in Woodbridge). The second dealt with the DOT’s presentation, saying she was “heartened” by what she had heard today; and on reliability issues. Questions to the two focused on the DPH’s authority on EMF; the definitions of “residential areas”; the applicants’ ability to work out a “prudent avoidance” plan for EMF while they were at the D&M phase; local bypass matters; the point made about deficiencies in the BMPs; and, finally, the issue of opening up Phase I again so as to “re-allocate” additional miles of undergrounding to Phase II.

 

 

March 29, 2005

Connecticut Siting Council Meeting

In the morning, the Siting Council finished reviewing its Findings of Fact. In the afternoon, Council members reviewed a preliminary draft of their final decision, but without signaling what its decision would be on some of the more controversial issues. Instead, they suggested these subjects would be especially suitable for oral argument.                                                                                                                           

                                                           PPPPPP

 1. Siting Council Findings of Fact. The Siting Council’s Findings of Fact (FOF), drafted by staff, includes some 800 findings culled from the hearings. Council members were asked to comment on them item by item: not for wording, but for general concepts. Starting in the morning, and continuing until lunch, the Council began where they had stopped on 3-23, and covered #632-the end. Each Council member offered comments, which the staff will incorporate. The main content of these findings were EMF and associated matters, such as mitigation, buffer zones, international standards, etc.  

2. Review of preliminary final draft. This preliminary draft wasn’t a complete document, and didn’t even include some of the points agreed upon in the last meetings “test” statements. Instead, it presented some of the general language necessary to include in the final decision about the Siting Council’s legal mandates; such introductory subjects as “Need and Reliability”, with a thumbnail sketch of transmission in CT; and the question of how to define “residential areas.” The draft also discussed the main proposed solutions (or alternatives) that the applicant or the Council has considered and rejected. The last general background subject covered was EMF. All of these sections were commented on and revised extensively, with many references to and citation of PA 04-246, as now codified.

 Finally, the draft dealt with the three most controversial local route changes in what will likely be the overhead portion of the line—leaving each one open. The three local changes are at: 1) Royal Oaks neighborhood ( Durham ); 2) B’Nai Jacob Congregation/Ezra Academy ( Woodbridge ); Jewish Community Center ( Woodbridge ). The draft presented separate “straw” paragraphs in favor of the route changes, against them, or alternatives, so that Council members could discriminate clearly among their choices. Meanwhile, oral arguments were invited on each choice.  

The other subjects especially invited for oral arguments were these.

            --The definition of a residential area, including an operative date. (The definition favored in the draft is simply “an area where people live”, as opposed to an area where no one lives, but this leaves open the question of “where people live as of when?”)

            --A framework to guide the final decision regarding EMF (mG) levels, consisting of 4 possible standards: 1) the (low) standard; 2) the (high) European standard; 3) the “no net increase” standard; and 4) the so-called “Lincoln Rd.” standard suggested by a Council member on 3-23 (see notes), which uses the mG level from underground transmission lines as a benchmark.

            --The meaning of “prudent avoidance”, particularly the extent to which it should involve cost.

            --Whether or not PA 04-246 applies to Docket 272.

 3. Costs. A supplemental sheet regarding costs for various alternatives in Docket 272 was reviewed and revised, similarly to the other FOF.         

4. Oral Arguments. A schedule has been sent out from the Siting Council, giving the general rules for the day of oral arguments on 3-31.

March 23, 2005

Connecticut Siting Council Meeting                                                                     The Siting Council rescinded its Best Management Practices document of December 2004, per the request of the Attorney General, and replaced that document with 1993 version.  Further, the Council reviewed its Findings of Fact re Docket 272. It also made a start on its decision for Docket 272: it signaled only 24 miles of underground, per the proposed route, with the rest overhead.

As to issues of the nature of a buffer zone, the precise definition of statutory facilities, and others—no consensus was evident; it was the same on some of the proposed town-specific variations along the route.  All of these matters will be debated during oral argument on March 31. A schedule was outlined leading up to the final decision on April 7.

PPPPPP

1. Best Management Practices (BMPs). Discussion on rescinding the BMPs, which had been suggested by the Attorney General, focused on two points. Presuming that the 1993 BMPs will be replaced during some future open hearing process, which BMPs—2004 or 1993—will be applied to the D&M portion of Docket 272. Moreover, which BMPs are meant to apply in the case of other dockets the Council considers? Without resolution on these questions, the December 2004 BMPs were unanimously rescinded, and the 1993 BMPs accepted in their place.

2. Siting Council Findings of Fact. The Siting Council’s Findings of Fact (FOF), drafted by staff, includes some 800 findings culled from the hearings. Council members were asked to comment on them item by item: not for wording, but for general concepts. Starting at 11 a.m., and going until 4 p.m., with a lunch break, the Council covered 631 of these findings, leaving the rest until March 29. Each Council member offered comments, which the staff will incorporate.

3. Initiation of preliminary final draft. Declaring that “every decision has to start from somewhere”, Chairman Katz posed a list to Council members of 26 “test” position statements re Docket 272.  She proposed to go through these “test” statements seriatim, with members responding, “Agree”, “Disagree’, or “Discuss.” She said the purpose was not to move any decision right now, but just to focus members’ attention and establish a preliminary direction for a decision. Also, the “test” exercise would help attorneys focus their oral arguments on March 29. The list of questions follows, with brief notes on the discussion.

            1. The need for a 345kV update has been established. (All agreed)

            2. A “no-build” decision is not a solution. (All agreed)

            3. The primary route proposed by the applicants is the best route, as opposed to any of the alternative routes. (All agreed)

            4. Railroad, submarine, and state highway (e.g. Route 15) routes are not feasible. (All agreed)

            5. The “ East Shore Route ” is not feasible, and requires expansion of an existing ROW. (All agreed, but members also pointed out that more than an expanded ROW would be needed.)

            6. HVDC is not a reliable solution. (All agreed)

            7. Underground construction at a distance of  24, 13, and 4 miles is minimally reliable. (All agreed)

            8. 13 miles is more reliable than 24, but PA 04-246 requires maximum UG, and 24 miles is feasible. (Discuss: A member raised a question as to whether PA 04-246 even applies to Docket 272, since the Act post-dates the application. Assistant Attorney General Robert Marconi remarked that no brief had challenged the Act’s applicability.) Oral argument was requested on the applicability point.

            9. No more than 24 miles of UG is technically feasible. (All agreed) Oral argument was requested on the location of any added UG, should any further miles be judged feasible.

            10. The buffer zone should be considered the width of the ROW. (Discuss). Oral argument was requested on this point.

            11. The goal for mG near statutory facilities should be 3-6mG at the edge of the ROW. (All disagree) This was the statement that generated the most discussion, with the issue being the level of mG specified. Broadly speaking, 4 positions were voiced. 1) The level should be 3-6mG. 2) The level should be “no-net-increase.” 3) No level should be specified. 4) The level should be the same as the mG associated with UG cable, given that PA 04-246 makes UG an “absolute” standard. Oral argument was requested on these points.

            12. Where no statutory facilities are located, low-magnetic-field design is not necessary. (Discuss)

            13. Residential areas (as statutory facilities) should be defined as 1) existing residences, 2) approved building lots, and 3) planned subdivisions. (Discuss) It was agreed that some cut-off date for the existence of a residence, approval of a building lot, or plan for a subdivision needed to be specified, and the general sentiment was that the date should be the date of the application, but oral argument was requested on the point.

            14. “Adjacent to proposed route” means abutting the ROW. (All agree)

            15.  Split phasing, tower height, or tower placement may be used to mitigate EMFs. (Discuss) One member pointed out that this statement may or may not be relevant for the decision, depending on whether a mG buffer is established.

            16. During the D&M phase, town officials may negotiate with the applicant re split phasing, tower heights and placement, depending on local needs and circumstances. (All agree)                                                                                   

             17. Although a link has not been proven between EMF and childhood leukemia, prudent avoidance of EMFs  is advisable. (Discuss) Members pointed out that the 1993 BMPs newly re-accepted recommend prudent avoidance; but they wanted to hear oral arguments on what “prudent avoidance” should mean, and, in particular, whether it should be defined around cost.

            18. A 15gW loading is a reasonable basis for determining EMFs. (All agree)

            19. Supported re-routings:

a. At Royal Oak , the line goes along the bypass/along the existing ROW. (All disagree) Members were split as to whether the line should go along the northerly bypass or stay in the existing ROW with a low-magnetic-field design.

b. In Cheshire , the line goes UG in the vicinity of Old Farms Rd. (All agree)

c. In Woodbridge , the line jogs on the grounds of Ezra Academy . (All agree—but feel the re-routing should be handled during the D&M phase)

d. In Woodbridge , the line jogs on the grounds of B'nai Jacob. (All agree—but feel the re-routing should be handled during the D&M phase)

e. In Bridgeport , the line jogs at the Pequonnock River. (All agree)

f. In Westport , the line jogs at the historic district. (All agree, after some discussion)

g. In Norwalk , the line jogs in the vicinity of the cemetery. (All agree)

            20. We recognize that the costs of Phase Two may not be socialized but could be borne alone by CT ratepayers. (Discuss) Some members felt that the decision should not include any statements on cost socialization.

            21. Statements re the locations of sub-stations (proposed for straw vote by Ashton):

                       a. Location of East Devon substation per proposal. (All agree)

                        b. Location of Beseck substation per proposal. (All agree)

                        c. Reject location of substation at Black Pond (All agree)

4. Schedule. Comments on the Siting Council’s FOF are due by March 29. When the Council meets on that day, they’ll finish #632 to the end of their FOF. They’ll also discuss further their preliminary draft decision, after which that preliminary draft will be forwarded to all parties and intervenors. The meeting on March 31 will be the time for oral arguments on the preliminary draft. On April 1, Council members will receive an updated draft of their FOF for further annotation. At a meeting on April 5, the FOF will be finalized, and any changes in the draft opinion will be made, based on the March 31 oral arguments. On April 7, the Council will take its final vote on Docket 272. 

March 15, 2005

Connecticut Siting Council Meeting

At a regular meeting, the Siting Council voted to take into the record for Docket 272 a letter from the Attorney General to the Council, and Chairman Katz’s response. Also discussed was the schedule for Docket 272 at the end of March. [The Council still expects to make its decision on Docket 272 on April 7, 2005.]                                                                                                                                   

PPPPPP

1.Attorney General’s Letter and Response. The letter from the Attorney General is dated March 8, 2005, and deals with two matters: 1) certain alleged ex parte conversations between the companies’ employees and the Siting Council about its “Electric and Magnetic Field Best Management Practices” guide (December 2004); and 2) KEMA’s change of opinion about the feasibility of putting more than 24 miles of Phase Two underground. Chairman Katz’s reply, dated March 14, 2005, responds in detail to these two matters, and includes signed affidavits from Siting Council staff.

2. Schedule. Three meetings will be held at the end of March concerning Docket 272. On March 23, the Council will deliberate their findings of fact, and give directions to the staff concerning the proposed final decision. The staff will write up a draft. On March 29, the Council will complete deliberation on their findings of fact, and look over the draft, after which they’ll circulate it to the service list. On March 31, from 10 a.m. to 5 p.m., the Council will hear oral arguments on their proposed final decision from any attorneys representing Parties and Intervenors who wish to speak. Those will be the final events preparatory to the decision on April 7.

  February 22, 2005                                                                                                          Siting Council Notification

Connecticut Siting Council Schedule

 

Thursday, February 17, 2005

Evidentiary Hearing  

The day began with testimony and cross-examination on Monday’s technical meeting, further consolidating the technical evidence around a route with 24 miles max underground. Next came a brief “clean-up” re 3 town-specific issues and questioning of the companies by the attorney for DOT. The last item on the agenda was two Council votes on motions from Wallingford/Durham 1) to rescind the Best Management Practices (BMPs) drafted by the Council last year; and 2) to dismiss the application altogether: the first motion was tabled; the second was denied. At that point, shortly after 5 p.m., the record for DOCKET 272 was closed. 

PPPPPP  

1. Testimony and cross on Monday’s technical meeting. At Monday’s technical meeting, the KEMA, ROC, and Dr. Boggs [re GITL]) had been asked to file statements with the Council outlining their agreement or disagreement with the other groups. These statements Links on this page at February 15 entry) were entered as testimony, and each group was cross-examined on its position. KEMA said that it now agrees 24 miles of underground is max: they no longer believe even 5 extra miles are feasible. Although Dr. Boggs continued to argue for GITL, he was pressed on its safety and reliability for long lengths in public roadways. He also continued to assert that XLPE was less reliable than GITL, because of special problems with XLPE’s manufacture and testing. He recommended diversifying vendors and even suppliers to vendors. He did not, however, recommend abandoning XLPE for underground purposes entirely. ISO and the companies reiterated that they will not be comfortable with more than 24 miles underground, and ISO seemed to imply that any further distance could not be “socialized”, meaning, costs shared around New England .

 2. Meriden , Woodbridge , Wallingford/Durham. Meriden did not testify, but submitted an affidavit that the Council will take up “in-house.” Woodbridge citizens testified about how they would like the line to be relocated around the JCC and Ezra Academy , if the line should go overhead. Finally, evidence was presented about the height of towers in the Valley View section of Wallingford , per different scenarios, and EMF levels at the Royal Oak neighborhood of Durham were discussed, per different scenarios. One citizen brought out the fact that what the companies call “existing” EMF levels calculated anywhere along Phase 2 are actually “future” levels, because it’s assumed in the current flows used for the calculation that Phase 1 has been completed.

 3. DOT. The DOT’s attorney focused his questioning on the “avalanche effect”, an acceleration in the normal “creeping” of underground cable, which can sometimes cause cable failure. The companies asserted this is not a large problem, and they expected the normal maintenance schedule for underground cable to be about 2 years. 

4. Wallingford/Durham Motion. Wallingford/Durham made a motion with two parts, amounting to two separate motions. The first was to rescind the BMP’s drafted by the Council last year; the second was to dismiss the application altogether. Both procedural and substantive arguments were made in favor of the motions, and also against them. The Council came to a vote on the dismissal motion first, and denied it without prejudice. The rescission motion was tabled. Council chair Katz asked for briefs to be submitted on various points brought up for and against the motions, so these could be dealt with at the time of the final decision. She emphasized, in particular, that while the attorneys had argued against reserving substantive matters for the D&M phase, she saw such a reservation as giving the towns more chance to participate, not less, and, in the end, as leading to a “customized” route.

5. Close of record. The evidentiary phase of Docket 272 has ended. Next steps will be for all parties to file briefs, as necessary, and for the Council staff to present the record’s findings of fact. A schedule for all those dates, and others, will be outlined on the Council website. The date for the Council’s final decision is still set for April 7, 2005.

Tuesday, February 15, 2005

Follow-up Reports to the Technical Session

KEMA

NU/UI Report on Technical Session

 

Monday February 14, 2005

Technical Session: Siting Council Consultants KEMA and ROC

Today’s technical meeting was called to allow KEMA and the ROC group to have the opportunity to find a reconciliation between the conclusions of the ROC group and the assertions of the final KEMA White Paper. [The ROC Report argues that only 24 miles of Phase 2 can be constructed underground, while KEMA, the Siting Council’s consulting expert, has argued that up to 20 more miles more are feasible.] The overall conclusion, essentially, was that the ROC Report stands: in terms of feasibility, 24 miles of underground is max.

PPPPPP

1. Format. The ground rules for this meeting were not the usual Evidentiary Hearing format. The facilitator was the Executive Director of the Siting Council, Derek Phelps. No Siting Council members were present: only the KEMA experts, power company experts, and other. Ideas were exchanged directly, not through attorney mediators. A tape was kept, and a transcript will be made, but none of the data or the discussion automatically became part of the evidentiary record. The effort was to identify precisely where the experts can agree on feasibility issues re Phase 2, and where they still disagree.

 2. New Data. In a white paper originally responding to the ROC Report, KEMA argued that C-type filters could mitigate harmonics problems identified by ISO-NE, and justify more than 24 miles underground; they further pointed out that the data so far reported by GE did not prove more than 24 miles underground would be infeasible; and they demonstrated that in rejecting a C-type filter solution the ROC Report had offered no hard evidence. Today, GE consultants offered detailed transient studies to justify their rejection of a C-type filter solution; moreover, the companies cited EnerNex studies circulated last week that also provided further evidence against the feasibility of more than 24 miles. Thus, quite a bit of new data was on the table. Most of the discussion about the new data centered on whether filtering could be designed so as to make more than 24 miles of underground feasible.  

3. Areas of Agreement. KEMA all along has agreed with the companies that 4, 13, and 24 miles of underground are feasible, and that the HVDC option may not be operable, nor does it allow sufficiently for new generation to come into SWCT. Faced with the new GE and EnerNex studies from last week and today, KEMA agreed that up to 20 more miles of underground is not feasible. They also agreed that “trading” segments of the proposed 24 miles to achieve some undergrounding north of the Housatonic would not be feasible.  

4. Areas of Disagreement. KEMA maintained that 5 additional miles is a “gray area”, and may still be possible, although they understand that the companies may not want to take the risk. KEMA also felt that some filtering should be done at certain sub-stations to mitigate predicted high voltages there. The companies and ISO-NE refused to consider more than 24 miles, saying the system is already at the edge of inoperability with that length. They did move toward some filtering at certain sub-stations, saying they might try it and see how it worked in non-critical situations. KEMA expressed satisfaction that this testing, so to speak, might open the door to further use of filtering for system reliability, but the companies did not particularly second this optimism.

 5. An Outlier Opinion. Although the main discussion today was between KEMA and the power companies, another pair of experts also participated, and they advocated an entirely different solution involving another technology, namely, GITL (Gas Insulated Transmission Line). Pointing out that the 24 miles of underground is not a distance problem, per se, but a problem of how much capacitance is in the system, they said the basic solution would be to reduce the amount of capacitance. GITL, they stated, is a type of line with very little capacitance, so if GITL were used, the underground portion of the line could extend much farther than 24 miles. This opinion has been testified to earlier, and the companies responded similarly today. They said: 1) that this technology has not been used for bulk transmission before; 2) that it would be difficult to construct and maintain for long distances. The other experts argued that GITL was at least as established

Tuesday, February 1, 2005

Connecticut Siting Council Documents

February 14 Technical Session

Proposed Schedule for Docket 272

 

Tuesday, February 1, 2005

Evidentiary Hearings

Today’s hearing covered updates on the subjects of EMFs, costs, and buffers. 

PPPPPP

1. EMFs. The morning began with a cross-examination of Drs. Bailey and Cole, regarding their comments on the most recent testimony about EMFs by the Drs Bell and Rabinowitz.

The discussion moved on to the issue of how a buffer zone to mitigate EMFs should be established. Questions were first raised about the way in which the Applicants take MF field readings (registered in milligauss, or mG), and how they calculated the current on the line (load). Drs. Bailey and Cole were asked if there were any scientifically-based way to set a buffer zone, as opposed to a judgment-call based on “prudent avoidance.” In their opinion, there’s no scientifically-based number of “unsafe” milligauss from which to calculate a buffer zone. They believe the international safety codes used by transmission engineers to set ROW boundaries are the only universally-accepted standard. Council members spoke of their concern about having to make recommendations about involuntary exposure to EMFs (via transmission lines), while voluntary exposure to EMFs (via appliances and other electronic devices) also are potentially harmful. 

2. Costs. The OCC (Office of Consumer Counsel, the State agency that serves as the consumer watchdog) is concerned about the reliability of the Applicants’ most recent cost estimates, which they have presented in ranges, as opposed to single figures. The OCC’s attorney asked the Applicants to come up with further detail about these ranges and asked what will determine whether the final costs will be at the low or high end of the range. The Applicants answered that the major drivers are: 1) the change in cable type (original proposal vs. ROC report) from HPFF to XLPE; 2) the price of steel and other materials to be used in construction; 3) the currency exchange rate (given that many of the materials are obtained overseas); and the extent of the new equipment (surge arresters, etc.) that will have to be added to strengthen the system’s reliability.

3. Buffers. The Applicants first displayed, onscreen, updated aerial maps of the 6 mG buffer option all along the portion of the route currently proposed to be overhead: Middletown to East Devon. The maps were drawn incorporating low magnetic-field design for each section of the route. Each statutory facility was indicated on the maps, with its distance from the line, and cross-sections of the tower designs, plus heights, were interspersed as necessary. The group viewed each town’s portion of the route in detail, with the Council and attorneys asking questions along the way. In some cases, alternative routes have been suggested by towns; and these alternatives were also shown and discussed, with the focus on which ones the Applicants currently support.  

Buffer discussions have come up in response to the public’s health concerns and the relevant Public Act passed during the last session; however, today certain environmental issues were discussed also, such as the impact of low-magnetic-field design on trees, wetlands, and underlying hydrology. A crucial summary question from Council chair Katz was this: if the Council were to order a buffer zone defined as giving no more than a 6mG magnetic field at either edge of the ROW, could the Applicants’ design mitigation techniques (tower heights, tower distances, etc.) to meet that order? Prete answered “yes” for UI. For CL&P, Bartosewicz answered, “We’ll look at that and get back to you.”

The Applicants next displayed similar updated aerial maps of the proposed underground portion of the line: East Devon to Norwalk. These maps also showed statutory facilities. The Applicants stated that wherever statutory facilities were near the line for short stretches it would be possible to install steel plates as shielding. Not as many questions were asked about this portion of the route, but some testing and negotiations are still ongoing about whether or where the line will cross the Norwalk River; and the DOT underlined its objection to the full 24-mile underground route, on account of construction issues.

Tuesday, January 26, 2005

Connecticut Siting Council Document

Confirmed Hearing Schedule for February

 

Friday, January 21, 2005

Connecticut Siting Council Document

Proposed Hearing Schedule for February

 

Thursday, January 20, 2005

Evidentiary Hearings

 

Today's hearings were focused on continued testimony on the issue of EMF. There was a brief meeting of the Council (this is not a hearing, it is a meeting of the Council to decide specific issues, as happens every month).

PPPPPP

 

1. First Selectman Amey Marrella, Woodbridge, made a brief statement of limited testimony.

 

2. The Woodbridge Educational Institutions testified on issues of EMF levels at their institutions and routing to protect the children that attend this locations.

 

3. The panel on EMF was again cross examined by the Applicants and the Siting Council as to safe levels of EMF and how guidelines should be established.

 

4. The meeting of the Council concluded that there will be a hearing (EMF continued) on February 1. There will be an announcement early next week as to further dates. There is a proposal on the table for a technical session for KEMA and the experts involved in the ROC report to take place on February 14. There would then be a hearing for a follow up to that session on February 17. We will report that information as it arrives.

 

Wednesday, January 19, 2005

Evidentiary Hearings

Today’s hearings brought more statements from elected officials. These statements were followed by presentation and cross of information about the proposed “Durham Bypass:. The day ended on cross of the Applicants about anticipated failure rates for the underground portion using XLPE (cross link polyethylene solid dielectric cable).

KEMA, the consulting hired by the Siting Council to advise on this docket issued their observations on the ROC report. You may use this link to read that report: KEMA: Observations on ROC Final Report

PPPPPP

1. The day began with statements of limited testimony by Representative Ray Kalinowski, Durham, Mayor Bill Dickinson, Wallingford and First Selectman Ken Flatto of Fairfield. 

2. There was discussion about Linda Wilson of Middletown, being able to change her status from Intervenor to Party. She was granted this status and became a Party called “The Wilsons”. The Wilsons presented their expert witness regarding the so-called Durham Bypass: what it would do to their properties and their suggestion as to technology to be used if the bypass proposal is used. There was cross examination about this technology (GITL or gas insulated transmission line) and how it would work with the bypass. 

3. The Siting Council had a number of technical questions about the technology, the differences between this type of underground cabling and the XLPE that is currently proposed for use in the Segments Three and Four undergrounding. 

4. The rest of the day was focused on the questions raised in previous hearings regarding failure rates of the XLPE cabling. It was established by Roger Zak, transmission services, NU, John Prete, project director, of UI and Anne Bartosewicz, project director, NU that they are comfortable with the fault or failure rates as they project them. They were closely questioned about that issue and there was discussion about the provision of documents to support their contentions.

 

Tuesday, January 18, 2005

Evidentiary Hearings

A schedule was proposed by the Siting Council, going forward. Legislators came to speak on their constituents' views. Testimony in the morning addressed concerns about the proposed route through Milford and Meriden; in the afternoon, testimony addressed the issue of costs and of underground cable reliability.

PPPPPP

1. Siting Council Chairman, Pam Katz, presented her ideas about the schedule for the final decision. The towns will not ask for any more technical studies, nor will the Siting Council. KEMA, the Council's technical consultant, is preparing a white paper on technical issues. Having read a draft, Chairman Katz feels that when the KEMA report is completed, Applicants' technical experts and KEMA should sit down and talk: she envisions a technical summit in early February. Although parties may observe, this will be a working session only. If more studies are requested after that, they'll be quick and focused. If the Siting Council is comfortable with closing the record by mid-February, they'll issue a decision by April 7, their current deadline. If they don't feel comfortable closing the record by mid-February, they'll issue a final decision by April 7 that will serve as a marker for a "replacement" decision to be issued soon thereafter. (While this may sound complicated, the decision for Phase 1 went through a similar process.)

2. Legislators who gave statements during the day were Senators Herlihy and Fasano as well as Representatives DelGobbo, Adinolfi, and Klarides. Both Herlihy and DelGobbo expressed strong reservations about costs, saying that the relevant legislation does not require the Siting Council to ignore costs, and noting the very large increase in cost estimates surrounding different buffering techniques, including underground.  Fasano, Adinolfi and Klarides stressed that the law requires citizens to be protected adequately, and questioned whether that was being done to the full extent. Saying that they were not opposed to the Siting Council, but trying to do their best for the people of the state, they urged the Siting Council not to be "bullied" by ISO or by the companies into a restricted amount of undergrounding.

3. The City of Milford presented a panel of witnesses who were cross-examined re: the number of properties that would be adversely affected in Milford under various buffer scenarios. Also discussed were the placement of the proposed East Devon transition station, and the impact of various buffers on Eisenhower Park.

4. City of Meriden also presented witnesses who proposed an alternative route within Meriden on property owned by the city.

5. On costs, company witnesses were cross-examined by counsel for OCC, DOT, and various Towns. Some of the questions covered how the companies had come up with the estimates. Mainly, the worries are that costs may grow even larger than the now estimated $900 million plus dollars. A great deal of the discussion referred to the growth in costs for Phase 1. The Applicants' witnesses generally answered that they don't expect costs to escalate greatly, because they've gained experience from Phase 1, and because they've already done some of the detailed tests that had not been done early in Phase 1. When asked to put a number on his confidence that the costs would not increase substantially, United Illuminating's project manager, John Prete said 80%, and when asked to quantify the level of design work that had been completed, he said 30%.

6. Mr. Roger Zak, Transmission Services, Northeast Utilities, presented a table of calculations regarding failure rates in underground XLPE cable. He testified, in summary, that these failure rates represented an acceptable level of risk.

Thursday, January 13, 2005                                                                                Evidentiary Hearings

The main agenda today was further testimony on the ROC Report, cross-examination, and redirect. Almost all of it had to do with technical engineering matters.

PPPPPP 

1. Pam Katz, the Siting Council chair, asked everyone to concentrate on “two simple truths”: 1) that the law requires the Council to site the maximum length feasible in Phase 2 underground; and 2) that buffers must be provided to protect public health. She said she would do her utmost to develop the record on these simple truths. She emphasized that ISO’s recommendations do not determine the Siting Council’s process and decision: the Siting Council has its decision-making job and the ISO has theirs. (Theirs comes in a regulatory proceeding known as “18.4”).

2. Questioning began with the Siting Council’s staff and members putting tough questions to the experts and ISO officials about certain omissions or confusing points in the ROC Report, and attempting to elicit brief answers, rather than long, complicated justifications. Questions were pursued about whether the proposal’s 24 miles of underground could be divided into 2 segments; about what kind of underground cable should be used; about why the ROC Report rejects the ABB proposal for a DC solution; about why the ROC Report rejects the KEMA proposal for using C-type filters as a mitigation to achieve further miles of underground; and about whether the 24 miles recommended by ROC could be stretched any further, even slightly.

3. One matter came up outside of Phase 2, but related. A federal group’s recommendations have resulted in a White House executive order regarding the environmental and public health impacts of energy projects. A Council member moved that the Council write to this group and ask for certain guidance regarding environmental and public health standards to be applied in Phase 2. This motion was rejected, however, because the group has not yet published its report, and also because it will disband on January 20.

4. The cross-examination by attorneys from various municipalities was exclusively technical. Questions were pursued further about whether the 24 miles of underground could be located all at the eastern end of Phase 2; about whether the assumptions used by the experts for modeling were realistic or reasonable; about what kind of underground cables should be used; about details of the planned mitigations; about whether shorter lengths of underground (4 miles and 13 miles—both alternatives supported by ROC, though not recommended) would meet Phase 2 objectives other than reliability; and about how certain features of Phase 1 affect current options for Phase 2. One new set of questions was raised about how certain features of another transmission project, a proposed upgrade from Norwalk to Stamford, would affect Phase 2.

5. On re-direct, the companies’ and ISO’s attorneys asked questions allowing the experts to clarify or expand upon some of their earlier answers that appeared to raise problems with ROC Report conclusions.

Tuesday, January 11, 2005                                                                          Evidentiary Hearings

The main agenda today was testimony on the ROC Report. Almost all of it had to do with technical engineering matters pertaining to the Report’s recommendations.

PPPPPP

1. Most readers of these notes know that the ROC (Reliability and Operability Committee) Report (December 21, 2004) recommends building Phase Two with 24 miles underground from Norwalk to East Devon, proceeding on from there to Middletown overhead: in other words, more or less the same as the original application. Changes from the original include a different kind of cable, some minor route adjustments, and a “massive” (ROC report language) upgrade of surge arresters, transformers, and switching equipment to ensure reliability.

2. The ROC Report is accompanied by several appendices, some of which have appendices of their own: in other words, the report depends on a lot of data. Some seven consultant groups carried out these studies, and many of those experts were testifying today on their work.

3. All of the questions today came from the Siting Council members: there was no cross-exam.

4. Some lead-off questions asked about the procedures of the ROC Committee: who chaired each day, whether minutes were taken, how long sessions lasted, which consultants did what, etc. The answers to these indicated a team approach and many hours of hard work, with certain reports coming out of it attached to the Report, but with little to no working record.

5. The rest of the questions were technical, and asked about all aspects of the ROC Report: what assumptions were used in the computer models of the system; whether or not the proposed system would encourage new generation; whether or not the 24 miles of underground could be split into pieces and still keep the system reliable; how KEMA’s suggested use of C-type filters to extend the length of undergrounding was eliminated from consideration; how the margins of safety regarding temporary over-voltages were calculated; why “extra” miles of underground would not work, etc. Quite a few of the answers overlapped with testimony heard much earlier in Docket 272. Given the technical nature of the subjects, the experts sometimes were hard-pressed to explain their rationale for certain conclusions.

6. Cross-exam on the ROC Report will be conducted next week.

 

 

Thursday, January 6, 2005

FERC Technical Session

As promised in October, FERC returned for a follow up visit to monitor progress on the proposed transmission upgrade for a 345kV line in SWCT.  This session was much shorter and more focused on the immediate issue of the upgrade without the attention to alternative energy, renewable energy or distributive generation as in the first session.

 

There was a brief introduction by NU's VP, Dave Boguslawski. Ths was followed by more in-depth explanations of the ROC report, the KEMA report, cost of the project, cost allocations (potential) and next steps.

 

The primary presenters were United Illuminating, Northeast Utilities and ISO-NE. Questions were asked of them by panel members, with closest scrutiny coming from Attorney General Blumenthal and Senator Tom Herlihy, ranking member of the Energy and Technology Committee.

 

Questions from FERC questioned focused on the why for demand of undergrounding, costs, the impact of PA 04-246, the cost to the rate payer of the delays caused by those against the transmission upgrade and the need for solutions being implemented as soon as possible.

 

Derek Phelps, executive director of the Connecticut Siting Council gave a progress report on the evidentiary hearings and stated the siting would be made in 2005.

 

FERC Chairman, Pat Wood concluded the technical session stating there were no plans at this time for FERC's return but they would indeed, be watching closely.

 

Wednesday, January 5, 2005

Evidentiary Hearings 

The Siting Council rejected the towns’ request for an immediate delay in the hearing schedule, which they argued was necessary for them to evaluate the ROC Report of December 12, ’04. The Council instead set out an ambitious schedule to meet the current January 20, ‘05 deadline for ending the hearings, but they also indicated that on the afternoon of January 20 they will discuss how to go forward with the docket. Thus, although an open-ended delay was rejected at this point, a door was opened to slide the schedule backwards from the currently-planned April decision. 

The main agenda for the day concerned testimony on EMF from underground cables: particularly what the health effects are, what shielding options are available, and which of those would be practical to construct.  

PPPPPP 

1. The schedule from now until January 20 will be as follows:

            a. Next week’s hearings on January 11 and January 13 will be held as planned.

            b. By January 11, KEMA should submit a list of the studies they want to do in order to evaluate adequately the ROC Report, and an estimate of how much time the studies will take.

            c. By January 18, KEMA should submit a white paper responding to the ROC Report.

            d. By noon on January 18, the towns should file briefs specifying what studies they need to do in order to respond to the ROC Report, and estimating how much time the studies will take.

            e. By noon on January 19, the ISO and the companies should respond to the towns’ briefs.

            f. On January 20, currently planned to be the last day of hearings, a hearing will be held, but the Siting Council will then meet on the afternoon of January 20 to decide on how to proceed further with the docket.

2. EMF from underground cables.

            a. The discussion started with testimony about EMF/DC in underground cables. The companies’ experts said that since EMF/DC operates differently from EMF/AC, one cannot assume that EMF/DC will have the same health effects as EMF/AC. Consequently, they said, the health effects of EMF/DC have been studied separately from the health effects of EMF/AC, with some overlapping results in biological studies, but no overlapping results in epidemiological studies.

b. Questions from Siting Council members and cross-examination by the towns’ attorneys and others elicited lengthy discussions of shielding options for both DC and AC cables, particularly XLPE. Much of this material overlapped with questions and testimony from earlier hearings.

c. The DOT attorney pursued questions about shielding that related to DOT’s interest in not putting any buried portions of Phase II under major state highways.

Monday, December 20, 2004 6:13 PM

 

ROC (Reliability Operability Committee) Report

 for a brief review, you may read the "ROC Information Sheet"

 

Monday, December 20, 2004 9:24 AM

Connecticut Siting Council releases hearing and deliberation schedule. You may read it here or look at the Calendar for the information

 

EVIDENTIARY HEARING and DELIBERATIONS SCHEDULE

 

Wednesday, December 15, 2004

Evidentiary Hearings                                                                                            Today opened with brief statements by four chief elected officials from municipalities along the Phase Two line. All felt that the Siting Council should take more time and be allotted more funds to evaluate undergrounding more thoroughly, per the state legislation in favor of undergrounding. 

The major testimony of the day concerned the ABB Report. It offers a high-voltage direct current (HVDC) alternative to the proposed Phase Two, which transmits high-voltage alternating current (HVAC). Witnesses elaborated on the three options presented in the ABB Report, all of which involve undergrounding most of the way from Norwalk to Middletown. According to ABB, the HVDC approach solves the reliability problems ISO-NE has found in the proposed Phase Two.

PPPPPP

1.ABB. During early Siting Council hearings, it became evident that HVDC could be put underground reliably for longer distances than HVAC, and the Siting Council directed NU to follow up on this possibility: NU then hired ABB. As a worldwide company that is a leader in HVDC technology, ABB did feasibility studies to see if HVDC underground could meet the Applicant’s specifications for Phase Two.

2. The ABB Report. HVDC transmission is a fundamentally different type of electrical system than HVAC. It offers few problems with undergrounding; instead, the main problem ABB needed to analyze was the feasibility of embedding a SWCT HVDC line in a system that is otherwise HVAC.  They came up with three feasible options, all involving different combinations of new converter stations and other equipment to manage the integration. One feature of their study was that it covered only Norwalk to Beseck (a substation in Wallingford), and not the entire length of the line from Norwalk to Middletown. This was per order of the Applicants.

3. Discussion of the ABB Report. Much of the cross examination by the Applicant’s and ISO of ABB was contentious, the cross serving to challenge the very company hired by the Applicants. ABB was questioned closely about reliability in regards to a DC segment in the middle of an AC line. Questions were raised about expandability, what happens when there is new generation, for example. PSE&G, a generating company, also participated in the cross of ABB, also not in a supportive questioning.  The attorneys representing the municipalities pressed, in their cross, ABB to know if an HVDC line could be extended the whole length of the proposed route from Norwalk to Middletown, and ABB was unable to give them that assurance, stating they hadn’t been contracted to study the whole route. The cost of an HVDC alternative is clearly an issue, as new converter stations would have to be built from the ground up at certain points, to replace conventional sub-stations, but since ABB had not been contracted to examine costs in any detail, cost comparisons were not a major focus of discussion.

4. Next steps. At present, the Reliability and Operability Committee (ROC), a group of engineers from the Applicants and ISO-NE, are doing tests, running studies and evaluating all of the major alternatives so far suggested to original Phase Two proposal. The ROC report is due on or about December 20. It’s unclear what the ROC report will suggest, or whether its suggestions will focus on an HVDC alternative. Many good questions, yet to be answered, were put on the table regarding the use of DC in this project.

 

 

Tuesday, December 14, 2004

Evidentiary Hearings

Today brought major testimony on the KEMA Report. Witnesses elaborated on the main conclusions reached in the Report (October ’04), which were not only that the 24 miles of undergrounding already proposed for Phase Two can work reliably, but that 10-20 more miles of undergrounding can potentially be added. Those conclusions offer a key argument against ISO-NE’s claim that the proposed Phase Two will not be reliable, and a major alternative to Phase Two as proposed.

PPPPPP

1. KEMA. KEMA is the transmission engineering company hired by the Siting Council to offer independent advice on Phase Two. Although KEMA has advised on various subjects, during the summer it turned its attention principally to the reliability of undergrounding, since ISO-NE brought the regular Siting Council process to a halt by challenging the reliability of the undergrounding the companies had so far proposed.

2. The KEMA Report. The main reliability difficulty, according to ISO-NE, came from a certain electrical phenomenon called “harmonic resonances”, or “harmonics.” KEMA set out to analyze the harmonics problems identified by ISO-NE, and to see what could be done. They did their own computer modeling of the SWCT electrical system, using information provided by the companies, and came up with a modified design for Phase Two, using devices called “C-type filters” to eliminate the harmonics problems. These filters, and other special equipment, could potentially allow an expanded amount of undergrounding in Phase Two. The KEMA experts agree that more studies need to be done to confirm the reliability of their suggested design, and would like to collaborate with the companies in carrying out such studies.

3. More undergrounding details. KEMA witnesses clarified many details about the further potential undergrounding suggested in their report. Most of the discussion was technical, but, on matters more accessible to a general audience, witnesses said the added undergrounding could be “broken up”, as long as transition stations were properly planned, and that XLPE cable should be used, as opposed to the fluid-filled type of cable the companies propose. The KEMA witnesses also commented on certain issues involving the integration of Phase Two with Phase One.

3. Next steps. At present, the Reliability and Operability Committee (ROC), a group of engineers from the companies and ISO-NE, are doing tests and evaluating many of the same questions dealt with by KEMA. Their report is due on December 20. It’s unclear what they’ll suggest, or what relation their suggestions will have to the ones KEMA has offered, but today’s testimony made clear that KEMA’s approach has substantial promise. 

 

 

Friday, November 5, 2004

 

FERC announced another technical session for January 6, 2005 in Hartford at the Legislative Office Building. It will be a follow up to the October session. Please note, this is not a public hearing but the public is invited to attend. For the announcement, you may click here:

 

FERC ANNOUNCEMENT

 

Monday, November 1, 2004

 

Connecticut Siting Council Announces Hearing Schedule

(You may also go to Events Calendar  page in this website)

 

 

Monday, October 18, 2004

KEMA report is released today. It is critical to keep in mind that this report, while being very favorable for undergrounding, does not include all of the studies necessary to demonstrate the feasibility of the latest information. It is, however, the best news we have heard in a long time. You may access the report here:

 

KEMA Harmonics Analysis Report

 

Thursday, October 14, 2004

Evidentiary Hearings

Today brought major schedule announcements. The Siting Council also completed review and questions concerning the buffer zone maps, and, in regard to buffer zones, heard testimony by Dr. Ginsburg, Department of Public Health, clarifying some of his earlier statements on “prudent avoidance” of EMF’s. 

PPPPPP

1. Schedule. Due to delay in receiving the ROC report, the Siting Council has cancelled further hearings on Docket 272 until December. At that time, it will take up reports on an alternative to the power companies’ proposal that hasn’t been explored in detail so far: a DC solution underground. Next week, the Siting Council will send out a schedule for interrogatories and pre-filings leading up to the December hearings. Hearings on the ROC report will be scheduled for January, 2005. In the meantime, the Siting Council will devote its primary attention to the completion of Phase One (Docket 217), and to the Norwalk-Stamford “Glenbrook” project, Docket 292.

2. Buffer zone maps. Per the Siting Council’s request, the utility companies have presented fifteen large aerial maps showing the proposed overhead portion of Phase Two (Middletown to Milford), and overlaying outlines of three possible buffers to mitigate EMF's: a 300’ “distance buffer”, and two “milligauss buffers.” About a third of the maps were reviewed at a hearing two weeks ago, and the job has now been completed. As before, questions focused on: 1) a need for the maps to be updated, which the municipalities are in the process of doing (the underlying aerial maps were made in 2002); and the matter of exactly how the various “facilities” selected to be buffered, per the new state statute, should be defined. New questions arose regarding a) property easement law, and b) the comparative advantages and disadvantages of different methods to mitigate EMF's.

3. Dr. Ginsburg, Department of Public Health. Dr. Ginsburg has given testimony and been cross-examined before the Siting Council at least twice before regarding the health impacts of EMF, and was asked again to appear in order to assist the Siting Council with further clarifications on the general topic of “prudent avoidance.”  One line of questions concerned Dr. Ginsburg’s position within the Department of Public Health as a risk assessor, whose job is to estimate actual or potential degrees of risk to public health, rather than as a risk manager, whose job is to design reasonable preventions against risk to public health. Dr. Ginsburg stated that, in the case of EMF, designing preventions is best left to the Siting Council. Another line of questions brought out Dr. Ginsburg’s estimates of risk from EMF. He reiterated the Department’s position that “background” (.5-1 milligauss) are not of concern; that levels of 3-6 milligauss fall into a “gray area” where there is some concern about a risk to children’s health, but not enough data to provide convincing evidence; and that levels above 6 milligauss are specifically of concern. Further questions from the Siting Council brought up newer topics having to do with the comparative risks of EMF from underground cables vs. overhead, or from long-term low exposures vs. short-term, high (peak) exposures. Dr. Ginsburg and the Siting Council agreed on the difficulties of communicating with the public about EMF, given that many important questions raised so far have to be answered “We don’t know.”

 

Wednesday, October 13, 2004

FERC Technical Session

Today in Hartford at the Legislative Office Building there was a FERC technical session. We will be posting notes about the session by tomorrow (October 14). A critical development was the delivery of the executive summary of the KEMA report. KEMA is the technical consultant that has been hired by the Siting Council for Docket 272.

 

You may access the summary here:

KEMA Executive Summary

As promised, the notes from the technical session. Summary first, followed by more detail after the PPPPPP

The FERC conference on the CT energy infrastructure focused almost entirely on the Middletown-Norwalk transmission proposal (Phase Two), giving all parties notice that FERC wants the siting process to move more quickly and thinks cost considerations should be aired more widely. FERC commissioners' comments also revealed, however, that they want every possible option to be explored, and that so far they have confidence in CT's ability to arrive at a good solution. They plan to keep the heat on, as they scheduled a follow-up conference sometime during Dec. 15, 2004- Jan. 15, 2005.

PPPPPP

    Just about every issue in the controversial proposal received a hearing.  Participants were direct and frank. The agenda covered 1) the need for the transmission upgrade; 2) progress on Phases One and Two: 3) cost allocation; 4) safety issues; 5) new technology options; and 6) next steps. These notes will feature only selected items.

    1) The discussion on need did not put forward transmission as the only possible solution, but also ranged into the need for new generation and load response programs. The utility companies stressed that new generation can only be encouraged sequentially after a transmission upgrade is done, due to interconnection problems in the system. CT participants also wanted to highlight for FERC that regional need is an important driver for the upgrade, not just the need in SWCT.

    2) The primary concern during the progress report appeared to be whether the utility companies and ISO-NE think the reliability issues can ultimately be solved.. Talk then progressed, in general terms, toward the idea of studying fewer miles of underground than the 24 originally proposed. The executive director of the Siting Council, Derek Phelps, then made available the executive summary of an entirely new report written by the Siting Council's independent consultant, KEMA (see link above) and stating, contrary to ISO-New England's opinion, not only that the original 24 miles of undergrounding proposed for Phase Two could work reliably, but that further undergrounding between Milford and Middletown might be possible. This was not open for further discussion, as the full report will have to be evaluated by the ROC.

   3) During the discussion of cost allocation, business interests protested that they had no idea of what actual costs might be for the alternate routes proposed, principally underground vs. overhead. FERC asked the utility companies to provide much more precise cost estimates to all stakeholders right away, rather than waiting until after a Siting Council decision. FERC posited that cost must be an integral part of the decision, not a separate matter. FERC also attempted to scale back CT's ideas about how much of the cost could be socialized.

     4) Safety issues (EMF) were discussed in the least detail. The technical expert mainly pointed out lingering uncertainties about the science. On the buffer question, he recommended a milligauss buffer rather than a fixed distance buffer.

    5) New technology options presented were new types of generation and more efficient conductors (wires). These presentations prompted one commissioner to remark that she would like to see a great many more new technology ideas in the proposals for Phase Two. The commissioner stated there is a need for government intervention, both federal and state, to assure transmission innovation.

    6) The discussion on next steps had various participants speaking about such subjects as the "unintended consequences” of the legislation passed last session calling for undergrounding and buffer zones, opening the process up to completely different proposals if Phase Two could not be proved reliable, and the importance of listening to the engineers before making siting conclusions on the basis of policy alone. ISO-NE said that ROC is discovering even more problems than they originally thought with an underground solution, and are uncertain about when they can present a report. FERC pressed them for a deadline, however, and participants reluctantly settled on December. FERC then asserted their authority by saying that they would convene another conference to ensure a conclusion, setting a date somewhere between December 15, 2004 and January 15, 2005.

 

 

Friday, October 8, 2004

Evidentiary Hearings Update 

 

Interim ROC Report

 

The interim ROC report was made available to the service list of Parties and Intervenors at noon before the 2 PM conference call. You will find the link to that report above. The questions posed to the ROC committee were very general. There was no timeframe laid out to the callers as to when to expect the final report.

 

Below you will find the "conclusion" section of the interim report copied and pasted from the .PDF file of the report linked above.

 

Today, at the end of the call, Derek Phelps, the executive director of the Siting Council, read the following statement written by Chairman Pam Katz:

Statement to ROC Committee

Wednesday, September 29, 2004

Evidentiary Hearings Update 

Today’s hearing focused primarily on the part of the Phase II route proposed to be underground through Fairfield County, not on continuing matters from September 28. It did, however, review material warning that burying the line is not as safe, in terms of EMF, as has been believed. The Department of Transportation (DOT) presented their routing preferences for Segments Three and Four (Devon Station to Norwalk, the original proposed underground lines). The hearings also covered some of the assumptions behind the basic design of Phase Two and various calculations regarding EMF. Finally, information was presented regarding who will pay for Phase Two or, more specifically, how that question will be decided. This matter involves a potential conflict between the state and the federal government.

PPPPPP

--In light of the unexpected testimony on EMF associated with underground cable, various ideas for shielding or other mitigations were discussed. The power companies downplayed two shielding options, one to put down metal plates over the cable, and one to bury the cable deeper. It was argued that the type of cable originally proposed (HPFF) will have the optimum shielding effect. This matter exacerbates the technical reliability questions about the Phase Two proposal raised in June by ISO-New England, and currently being investigated by the Reliability and Operating Committee (ROC).

 --DOT has told the Siting Council that it would like the underground portion of Phase Two to go under a minimum of state roads.  Their primary concerns is the traffic issues and safety hazards during construction. In response to a “homework assignment” from the Siting Council, they have submitted maps of their own preferred alternate routes, which favor local roads, and were present to discuss those alternates. Bridgeport, Fairfield, Norwalk, and Westport all expressed their preference, instead, for the Applicants’ proposed route. Since the same clash between the companies and DOT arose during Phase One, and is part of the reason why Phase One construction is delayed, the Siting Council has urged compromise. The Siting Council does have final authority over the route, but it believes everyone’s interests are better served by negotiation than by fiat. The DOT has made progress with the companies on Phase One, and that joint effort will help on Phase Two, but actual negotiations cannot proceed until a specific route is decided.

--There have been disagreements on some of the basic assumptions used in designing Phase Two from the beginning, and these were raised again today in a discussion of whether the EMF figures used to prepare yesterday’s buffer zone maps are trustworthy, especially going forward ten years. Assumptions such as how much transmission New England will need, how much peak need is weighted over average need, for planning purposes, how much power will be generated in CT, and similar guesses all figure into ISO-New England’s computer models of the transmission system, and in turn affect computer calculations of EMF scenarios.

--Derek Phelps, executive director of the Siting Council, circulated a memo he prepared about the powers of ISO-New England, the New England Power Pool (NEPOOL), and the Federal Energy Regulatory Commission (FERC) regarding rules on who pays for power projects. The memo gives highly detailed background information on each organization and on Phase Two, but helps to address who gets the bill—everyone in New England? only people in CT? only people in SWCT? only people in certain municipalities along the route of Phase II? Phelps emphasized that the Siting Council will not make this decision: it will be made by ISO-New England, NEPOOL, and FERC. This is not in the purview of the Siting Council but was done as a service to assist all of us in better understanding that process. Derek Phelps also asked for corrections and emendations to his memo.

--The next hearing is set for Thursday, October 14. The agenda will include further discussion on the buffer zone maps introduced yesterday, and a supplemental statement by Dr. Ginsberg, Department of Public Health, on EMF.

 

Tuesday, September 28, 2004

Evidentiary Hearings Update

(We will, going forward, offer a brief synopsis of the hearings followed by more detail. The two will be separated by PPP)

The hearing on Tuesday, September 28 underscored how difficult the choices are for both the Siting Council and CT citizens. The Applicants have, to date, not accepted technological suggestions that might what is known as the “East Shore alternative” possible. Second, unexpected evidence was presented that putting the transmission lines underground might not offer the protection against electrical and magnetic fields (EMF) that citizens had hoped for. Finally, new maps were introduced that illustrated how many homes would be impacted if the Siting Council were to require a buffer zone from Middletown to Milford of 300’.

PPPPPP

--The Applicants’ version of the “East Shore alternative”, which involves building an entirely new 345kV line from East Haven to Wallingford, is unacceptable to the new towns it would affect. Another version of the “East Shore alternative” that would likely be acceptable to all citizens, which involves simply upgrading the lines and facilities for an already-existing 345kV line, appears to be unreliable. According to the Applicants, the new lines, towers, or high-tech machines suggested for the upgrade would be too experimental and too expensive to be reliable.

--Evidence about the EMF associated with underground cables was presented by a consultant for the Applicant. It showed that burying the lines doesn’t necessarily take away any risk to public health, and may actually increase the risk.

--The maps were the most dramatic. They were prepared by the Applicants in response to a request by the Siting Council, as a “homework assignment.” The Siting Council intends to use them for guidance as they try to put in place a buffer zone recently mandated by a state law. Passed in response to citizen concern about EMF, the law states that a buffer zone should be created around new power lines to safeguard public health, but it does not define “buffer zone” exactly. Since EMF levels fall off with distance from the power line, getting down to background levels about 150’ from the line, a “distance buffer” could be formed by increasing the right-of-way where necessary to achieve 150’ on either side of the line, or 300’. Another way to create a buffer, however, would be to set a certain maximum milligauss (mG) level (EMF are measured by mG) and make changes in the design of the line itself in order to achieve the set mG level more or less within the established right of way. This could be done, for instance, by making the towers higher, or by arranging the lines, or conductors, in such a way as to make the EMF cancel itself out, or both. The Siting Council asked the power companies to prepare maps from aerial photos that would illustrate a “distance buffer” of 300’ and two “mG buffers”—one at an average level of mG, and one in an extreme case. The maps depict the numbers of acres and homes affected by the distance buffer. These maps only represent illustrations according to the “homework” specifications, however.

 

 

Tuesday, September 28, 2004

Utilities and ISO-NE Working Group Committee Update (ROC)

This was a very brief call as the anticipated reports had not been completed. it is expected that there will be an interim report in or about October 8 from the ROC.

 

Tuesday, September 21, 2004

Utilities and ISO-NE Working Group Committee Update (ROC)

Two key studies have been delayed. One (by GE) looks closely at whether undergrounding in Segments 3 and 4 can be made more reliable via the use of a more efficient cable and other adjustments. This is  Case 5. The other (by ABB) is to see whether the whole line can be made more reliable via the use of DC.

The Applicants expect  both studies will be ready next week, and they will be reported to all parties at the next ROC conference call, to take place  8:30 Tues AM., Sept. 28, just before the already-scheduled Evidentiary Hearing. That hearing, as well as the one for Wed., Sept. 29, will go forward with the agenda as planned.  The scheduling of any Siting Council's  hearings on Docket 272 past next week, however, will depend on the results of the ROC conference call on Tuesday.

Two other reports are important, and yet to come. One is a report on the Case 7, which tries to make undergrounding reliable and operable by adding several STATCOMS, high-tech devices for managing load-flows on the line, to the Case 5 conditions. The second is a report by KEMA, the Siting Council's technical expert. They are writing their own comprehensive review of reliability and operability, considering several earlier studies done for the companies in Docket 272, as well as ROC's recent work. KEMA's report is due October 8.

Wednesday, September 8, 2004

Connecticut Siting Council Technical Session

The morning session was devoted to legal motions.

  1. Towns of Durham and Wallingford Motion to update Council's Best Management Practices for EMF: Tabled to a later date

  2. Towns of Woodbridge, Milford, Orange, Cheshire, Wallingford, Durham and Middlefield Objection to Office of Consumer Counsel request for discovery: Sustained

  3. Town of Durham Motion to Compel: Deferred action/motion to withdraw

  4. Applicant's Motion for Protective Order: Portion of motion was withdrawn

 

Procedures for changes in oral argument for Council's draft Opinion were discussed. Changes were suggested and there will be a final proposal made at the next set of September hearings

 

Update on ROC working group. See below, Tuesday, September 7 notes.

 

Update on KEMA studies, the consultants hired by the Siting Council. There will be a preliminary report submitted on or about September 26. Final report is expected to be ready by October 4.

 

The afternoon session was a Public Hearing for the one issue of definition of "buffer zone".

Legislators, Mayors and First Selectmen and members of the public made statements to the Siting Council as to their individual definitions of buffer zones. Buffer Zones of 300 feet on either side of the line was generally recommended. The Siting Council also asked for comments on signage (delineating the edge of the ROW) as well as use restrictions within the zone.

 

The session concluded with Chairman Katz asking the Applicants to provide maps with 3 different options for buffer zones:

  1. 300 foot

  2. 3 mG zone at a 15 GW (gigawatt) loading case

  3. 3 mG zone using 27.7 GW loading case.

 

(Translation: There are a number of ways that are being considered to ascertain the actual definition of a buffer zone. Measurement in feet is one. The other 2 are based on current load and potential future load; how much power is likely to be flowing through the lines)

 

 

Tuesday, September 7, 2004

Utilities and ISO-NE Working Group Committee Update (ROC)

In today's very brief call, the following announcements were made:

  • The utilities have gone back to Case 5 to revisit and see if perhaps there is a way that can make it work. To that end, GE is doing a study on TNA (transient network analysis).

  • Regarding the 6 proposed Statcoms, at 4 locations, there will actually be 12 Statcoms at 75 MVA each at the same 4 locations. This does not effectively change anything from the lay persons' point of view.

  • The Companies are still working with ABB on a DC solution. it is expected that there will be a preliminary report on or about September 17.

  • There is not expected to be a call next week on the 14.  There will be one on the 21. Should that change, we will be notified and will, of course, let you know of any major developments.

 

 

Monday, August 23, 2004

Siting Council Hearing Announcement

Memo to all Parties and Intervenors, re: Docket 272

To prepare for your participation in the public comment portion of the September, please read the legislation attendant to the issue of buffer zones.

Public Act 04-246

 

Thursday, August 19, 2004

Process Hearing, Connecticut Siting Council

Parties and Intervenors met today with the Applicants and the Connecticut Siting Council to begin to look at next steps for Docket 272. 

There were many decisions that needed to be made and a number of issues to be addressed. 

 

The Applicants stated the final studies and report will be completed the first week in October. It is unlikely that there will be Evidentiary Hearings before that time. 

 

There will be a Hearing day on September 8 for motions to be heard on behalf of the Towns of Wallingford and Durham. That will take place the morning of the 8th. The afternoon will be a technical workshop, as it were, for the buffer zone. There will be more announcements about this technical workshop in the days to come.

 

 

Tuesday, August 17,  2004

Connecticut Siting Council announces suspension of Evidentiary Hearings

 

Monday August 16, 2004

ISO-NE Press Conference to Announce Report of the ROC to the Siting Council

 

Today, in a press conference called by ISO-NE it was announced that thus far, the ROC working group is recommending to the Siting Council that they propose a technological solution for the undergrounding of the 24 miles from Devon to Norwalk.

 

To read this report you may go to:

ISO--NE Report to the Connecticut Siting Council

 

The ISO stated that there are more studies to be completed and reliability concerns to be answered. There will be many questions to be asked and answered in the coming hearings;

 

Tuesday, August 10, 2004

Utilities and ISO-NE Working Group Committee Update (ROC)

Steve Whitley opened today's call and then turned the all over to the project directors, Anne Bartosewicz of NU and John Prete of UI.

 

John Prete explained the results of the studies for Cases 5B, 5C and 5D. Bottom line is that all three Cases fall below the standard set of the 3rd Harmonic, thereby eliminating them.

 

Anne Bartosewicz went on to discuss the working efforts with ABB, the DC experts. There will be a conference call with ABB and the technical people from the utilities. They are looking at an all DC solution going from Beseck to Norwalk. ABB is expected to submit their findings on Friday.

 

The next step is to examine Case 7. As a reminder of what Case 7 is, this is from the report explaining Case 7:

       "Start with the M-N proposed Project, replace both 345-kV HPFF cables between East   Devon and Singer with XLPE, replace both 345-kV HPFF cables between Singer and Norwalk with XLPE, remove one of the 345-kV HPFF cables in the Bethel to Norwalk Project from service, remove the 115-kV capacitors at Plumtree from service, reduce the capacitors at Glenbrook to 75 Mvar, and reduce the capacitors at Frost Bridge to 205 Mvar in the “all caps in” cases, and investigate fixed capacitor replacements with dynamic reactive control devices."

 

Thermal and voltage studies have begun already and according to the call, it is expected that the harmonics issue will be acceptable, that Case 7 will be above the 3rd harmonic. They will be doing short circuit testing next. There was also discussion about the use of Statcoms to reduce capacitance. They would be adding 6 of them along the entire system. That would be six 150 MVAR which would each require 1.5 acres at the cost of 40 million dollars each.

 

The final report and findings are still anticipated to be completed by next Monday, August 16. We will post the results at this site.

 

 

Tuesday, August 3, 2004

Utilities and ISO-NE Working Group Committee Update (ROC)

This was a very brief call as the studies  for Cases (alternatives) 5 B-D that had been anticipated for today's update had not come in.

 

The information that was reviewed, however, was the following:

  • While the studies had not come in it was learned that there are significant "issues" with Cases 5C and 5D, that being many short circuit issues which are "enormous"

  • The utilities will take a look at a modified Case 6. This modified Case 6 will replace capacitors with Statcoms (high speed or dynamic Vars)

  • It is still anticipated that the Applicants will meet the August 16 deadline.

 

 

Thursday, July 29, 2004

Evidentiary Hearing Update

The primary focus of today's hearings, after a brief statement and cross exam of Dr Ginsberg from the Ct Department of Public Health was DC cable technology.

 

Dr. Ginsberg's testimony was a revisit to the issue pf EMF levels relative to the buffer zone and the State's position of levels considered to be safe for children,

 

The highly technical testimony for DC cable technology reviewed the aspects of the interaction between the AC and DC systems, the need for convertor stations to allow the system to go from AC to DC and how to allow the systems to be strengthened to support the interaction of the two.

 

The hearings will continue in September, beginning again on Wednesday, September 8.

 

 

Wednesday, July 28, 2004

Evidentiary Hearing Update

What was to have been a brief cleanup of yesterday's buffer zone cross examination and direct testimony turned into all day. A great deal of time was spent reviewing and closely examining the evidence as presented by both sides regarding EMF levels and their impact on children.

 

Legislators representing PLUG, Power Lines Under Ground made a statement of limited testimony to the Siting Council regarding their expectations of interpretation of the law passed  this last session, 5418, known as Public Act No. 04-246 which speaks to undergrounding, buffer zones and EMF's. Senators Win Smith, Joe Crisco and Representatives Al Adinolfi and Themis Klarides came to the hearings to reiterate to the Council the demand for undergrounding of powerlines.

 

Tomorrow the hearings will be on DC cable technology.

 

 

Tuesday, July 27, 2004

Evidentiary Hearing Update

Today's evidentiary hearing was devoted to 2 topics: 

  • Strategies to reduce EMF levels 

  • Buffer zones

The three possibilities that were presented by the applicants for reducing EMF levels were

  1. Add distance, as in increased buffer zone 

  2. Optimize Phasing

  3. Optimize Combination of Structures

The Applicants put on the case for both EMF mitigation and buffer zones. Cross was begun on buffer zone issues and will be completed tomorrow.

 

The primary focus of the hearings tomorrow will be the Towns' preferences, where stated, for overhead and underground (or combinations of the two).

 

Tuesday, July 27, 2004

Utilities and ISO-NE Working Group Committee Update (ROC)

Today's call reviewed the new Cases, or alternatives, that have been added. These Cases, called 5A, 5B, 5C and 5D. Two of the new Cases add DC cable from Beseck Station (in Wallingford) to East Devon substation.

 

Two others add a 500 MVA synchronous condensor at East Devon and/or Singer substations. A MVA synchronous condensor is a generator without turbines that produces no watts. It can be set, as needed to consume or produce Vars (reactive energy). This is used to bolster a weaker AC system which is, as we are told, what we have here, in southwestern CT. 

 

 

Tuesday, July 20, 2004

Utilities and ISO-NE Working Group Committee Update (ROC)

According to the latest studies, Case 6 (to review: there were 12 "cases" or alternate solutions being examined. The ROC, (Reliability Operating Committee) created a flow-chart of sorts for the process. The plan was to begin with Case 5. If case 5 worked, they would move up to Case 4. If Case 5 did not work they would go to Case 6. As we learned in last week's call, Case 5 did not pass. Now we know that, again, do to harmonics, Case 6 did not pass.

 

Now the ROC, instead of going to Case 7, will now create new cases or options to examine. The focus will now be on DC cable technology. The reports of that progress will be the subjects of the call for next week as well as the Evidentiary Hearings that are schedule for next week, July 27-29. DC cable will be discussed on the 29.

 

It would appear from the call today that  the ROC is going in the direction of removing more capicitors to attend to the harmonics problems. We will report the outcome of the conference call here next week as well as the updates from the Evidentiary Hearings.

 

Tuesday, July 13, 2004

Utilities and ISO-NE Working Group Committee Update

The expected report from GE was reviewed. The gateway, or standard set for going to the next positive step was not met. Proposed changes for the first case studied did not produce the hoped for results and therefore failed the test for harmonics. 

 

The flowchart that was outlined in the first call of July 6, began the studies with Case 5. If that worked and worked well, the next step would be Case 4. since Case 5 did not meet the tests required, the examination will now go to Case 6.  The next step will be to do a harmonics scan as well as thermal and voltage analysis for Case 6.

 

Bottom line, good news and bad news. Bad news is that Case 5 doesn’t solve the problem. Good news is that taking capacitance off the system helps. Case 6 goes further in the direction of removing more capacitance 

 

Next call will review the three studies for Case 6 on harmonics, thermal and voltage analysis.

 

Tuesday, July 6, 2004

Utilities and ISO-NE Working Group Committee Update

Today was the first of the weekly update phone conferences. 

 

Work has begun on identifying "cases" that will be studied that might allow undergrounding to go forward. The process and "gateways" that must be passed in order to keep undergrounding were reviewed and discussed. There are 12 cases identified. These cases run from the best case scenario to the worst case. This is not an exhaustive list and it may be expanded as time and studies progress.

 

Issues boil down to reliability and the laws of physics that must be addressed in order for ISO-NE to be able to sign off on the new proposal. Harmonics, capacitance, and MVAR's** become significant. See definitions below.

 

There will be studies performed that will dictate next steps. The results of those studies will be a part of the update conferences as they are completed.

 

**MVAR:  (Megavolt Ampere Reactive) A reactive power measurement incapable of doing work.  Electrical equipment capacities are sometimes stated in MVAR.

 

Capacitance: The property of an electric conductor that characterizes its ability to store an electric charge. An electronic device called a capacitor is designed to provide capacitance in an electric circuit by providing a means for storing energy in an electric field between two conducting bodies.

 

Harmonic: A sinusoidal wave having a frequency that is an integral multiple of a fundamental frequency. For example, a complex wave whose frequency is twice that of the fundamental frequency is called the second harmonic. Harmonics in a power system cause distortion of the normal sinusoidal voltage waveform.

 

Wednesday, June 23, 2004

The "Process Hearing" proposed in last weeks hearing took place today. NU/UI presented a proposal to move forward. This proposal was discussed and the following are the outcomes of today's hearing.

  • There will be a committee consisting of Roger Zaklukiewicz, VP Transmission Projects of NU and Stephen Whitley of ISO-NE. The commitment was made by the Applicants to work to find a way to keep the undergrounding that was proposed in the application for Segments Three and Four Towns. The proposed changes will be submitted on August 16.

  • To keep the process "transparent" as put forth by the Assistant Attorney General, there will be weekly conference calls with the parties and intervenors.

  • July hearings (July 27-29)  will go forward, as scheduled. The focus of these hearings will be Segments One and Two overhead routing, EMF mitigation and "buffer zones" as addressed in Bill 5418. 

  • The changes to the application will be put forth on August 16.

  • There will be another "Process Hearing" to take place in early September to review what has gone forward and what will be the next steps.

  •  It is hoped that Evidentiary Hearings will resume in late September.

 

Thursday, June 17, 2004

ISO-NE gave the expected testimony today that the Phase Two application as proposed, cannot be operated reliably. The Siting Council hit the pause button and asked ISO-NE and the Applicants to confer about potential fixes. Town attorneys and the Assistant Attorney General recommended the Towns be included in the conferences as the process moves forward.

 

The alternative routes under discussion, such as the East Shore route,  are on hold for now.

 

There will be a "Process Hearing" at a time yet to be determined with the Siting Council and all Parties to discuss next steps for this procedure.

 

For action points, please refer to our Coalition Information page.

 

 

Wednesday, June 16, 2004

The day began with a revisit to the EMF panel. of experts from Woodbridge. The cross examination by the Applicants began on a contentious note; ultimately, things settled down and good information was put into the record.

 

The day concluded with a cross examination of the Connecticut Department of Transportation. The afternoon identified many issues that are problematic for undergrounding on State's roads. The problems will be addressed by the Applicant's as the project moves forward.

 

The primary focus of the hearing tomorrow will be the ISO-NE.

 

Tuesday, June 15, 2004

In this, the start to what could be the most critical week for this Docket 272, the day was spent on the reports by GE for the applicants. It was a very difficult day for all sides with the specter of the prefiled testimony submitted by ISO-NE calling into question the reliability of any undergrounding.

 

The cross examination by the Siting Council's own analyst was critical today. His questions were probative and on point, bringing out most salient points. What started as a dismal day ended on a very positive note as the Towns followed up on the Siting Council's cross their own cross examination of the experts from GE.

 

Tomorrow the issue of EMF will be revisited. There will also be testimony from Rep Al Adinolfi as well as the CT. DOT.

 

Thursday, June 3, 2004

In today's hearings the Siting Council heard testimony and cross examination on technical issues such as load flows and support for alternative routing. Also addressed today were environmental issues attendant specifically to Woodbridge and Milford.

 

The Siting Council, in continuing their efforts to "leave no stone unturned" has asked that each town from Middletown to Milford present routing for their town that would be acceptable to that town for both an all underground solution as well as an all overhead solution.

 

The hearings will begin again Tuesday, June 15 at 10 AM. There will be further discussion at that time on undergrounding. Wednesday, June 16 will be a continuation of the EMF issues as well as the day the CT DOT will present their case. Thursday, June 17 will be completion for issues that have not been finalized by that time, a clean up day..

 

Wednesday, June 2, 2004

Following a presentation by the utilities on various alternative routes, expert witnesses from the Office of Consumer Counsel (OCC) were cross examined. The OCC is the state agency responsible to the ratepayer, making sure the rates for any utility is within reason.

 

The northern route alternatives, as well as what has come to be called the "East Shore" alternative and Black Pond were discussed. 

 

Tuesday, June 1, 2004

The day began with the announcement that the CT Siting Council hired their expert. The company  is KEMA. You may go to their website: www.kema.com

A notice went out to the service list (all parties and intervenors) that communication with KEMA is considered to be ex parte communication, but we would encourage you to visit their website and learn about the company.

 

During the morning session, the Towns cross examined the utilities on issues of environmental impact. That line of questioning continued in the afternoon 

with a brief questioning by the Woodlands Coalition attorney cross examining the utilities on issues of underground technology.

 

Tomorrow's hearings are expected to cover the "East Shore" alternative with the utilities presenting their information about the alternative and the other parties and intervenors being allowed to cross examine them on that information.

Thursday,  May 13, 2004

Today was to have been the last day of hearings dealing strictly with the issue of EMF and health impacts of the proposed upgrade. There is much information to be covered and the task was not completed today. the issue will be picked up again in future hearings. Listed below are the future hearings dates and the subjects to be covered on  those dates.

·         Tuesday, June 1                     Overhead segments 1 and 2, supported segment changes, cable technology, substations, and construction impacts.

·         Wednesday, June 2                East Shore Route and all other alternative routes.

·         Thursday, June 3                    Ecological, historic, scenic and recreational values.

·         Tuesday, June 15                   Council’s Underground Transmission Consultant.

·         Wednesday, June 16              Continuation of Electric and Magnetic Fields.

·         Thursday, June 17                  Continuation of subject matter.

·         Tuesday, July 27                     GE Modeling.

·         Wednesday, July 28               GE Modeling and Council’s Underground Transmission Consultant.

·         Thursday, July 29                   Follow-up to all Witness’s Testimony/Clean-Up.

Wednesday, May 12, 2004

After a delayed start to the day, cross examination of the Applicants' panel of EMF experts continued from the March hearings. Before that process could be completed, Dr. Ginsberg of the CT Department of Public Health was given his opportunity to be cross-examined. the primary focus being the EMF and issues of health with both sides making some headway. The day of hearings concluded with discussion of adding extra days to the full hearings in order to allow for as much information to get into the record as possible.

 

Thursday, April 22, 2004

Alternative routes were the topic of today's hearing. A presentation was made by the Applicants of the various concepts of routing. This presentation was followed with  close questioning by the members of the Siting Council.

 

During the afternoon portion, the Council heard from the ConnDOT and the departments concerns about routing and construction.

 

The hearings will resume on May 12. The issue of EMF will continue at that time.

 

Wednesday, April 21, 2004

Today's hearings began with the cross examination of the Applicants by the South Central Connecticut Regional Water Authority of New Haven. The focus of the cross was regarding the presence of polybutene  in the HPFF (high pressure fluid filled) cable that would be used in undergrounding. 

 

The Siting Council continued their cross examination of the Applicants regarding underground technology and alternative routes. Tomorrow the issues of the use of highways and railroads as alternatives will be reviewed.

 

Tuesday, April 20, 2004

Today was the most contentious of the hearings thus far. The hearings began with the Applicants presenting their proposal for Segments 3 and 4, the Devon Station to Norwalk line. the attorneys for the Woodlands Coalition and the Towns of Weston and Wilton cross examined on the issues of reliability among others. 

 

The Connecticut Department of Transportation then began their cross examination. It was a very aggressive cross exam, going over many points. 

 

The afternoon was a review construction issues and the types of underground cabling available and why one would be preferable over another.

 

 

Thursday, March 25, 2004

The focus of today's hearing was the issue of EMF. The Applicants put up a panel of both outside experts as well as members of their team. Attorney General Richard Blumenthal cross-examined the panel. That cross was followed by Assistant Attorney General Charles Walsh who represents the Department of Transportation. Next, the panel was cross-examined by Robert Earley, staff attorney of the Connecticut Business and Industry Association (CBIA).

 

The day's cross examinations concluded with the opening statement by Dr. Gary Ginsberg, toxicologist from the Department of Public Health.

 

There were many tasks assigned to various of the witnesses and experts. The Siting Council, overall, asked that a lot more information be provided regarding EMF studies as well as specific information of EMF levels (projected) at homes as well as schools, camps, and childcare centers.

 

The following is the announced schedule for the rest of the hearings. While the April dates are firm, there is the possibility the dates for May and June might be altered. Please check our Events Calendar page for updates on any changes to the schedule. That is where we will note any changes to the schedule.

 

April

20-21 (Tuesday/Wednesday) Segments Three and Four (Devon Station to Norwalk)

22 Alternative routing: railroad, highway and marine

 

May

12-13 (Wednesday/Thursday) EMF The hearings from today will be continued at this time.

 

June

1-3 (Tuesday/Wednesday/Thursday) Segments One and Two, including East Shore Alternative and undergrounding

 

15-17 (Tuesday/Wednesday/Thursday) Finish cross on any outstanding issues.

 

 

Wednesday, March 24, 2005

 

Today, in a short hearing, the Office of Consumer put their expert witness, of Marc D. Montalvo, an economist and energy systems planner from the La Capra Associates’ Wholesale Market Analytics Group up for cross. He argued that an integrated plan should be developed instead of relying only on transmission. He was questioned about the practicality of doing this in SWCT.

 

Tomorrow: Utilities' panel of experts on EMF and the Department of Public Health

 

Tuesday, March 23, 2004

The "Towns" filed a Motion to Dismiss the application with the Siting Council and that motion was denied. 

Certain schedule changes were announced which will extend the hearings through June.

  • Segments Three and Four (Devon Station through Norwalk SS), the substations of those segments and certain alternatives will be taken in April

  • Appearance by State Representative Al Adinolfi on EMF and Undergrounding will take place in May and June.

  • CFRE2, on EMF will be in May

  • Woodbridge Jewish Organizations on EMF will be in May

  • Thursday's (March 25)  scheduled EMF hearing will only be presentation and cross examination of the Applicants panel of experts

  • Witnesses and Exhibits for EMF only will be in May 

Today, the Applicants and ISO-NE presented their case on the subject of need.  They were cross -examined by the Siting Council. Forays were made into the issued of socializing the cost of the project, gold-plating and undergrounding which are being examined by ISO-NE. The Siting Council asked ISO-NE to return in June with updated reports. The matter of FERC intervention was also raised.

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

As always, should you have any questions, please feel free to contact us at: CSCHearingsUpdate@woodlandscoalition.com

 

Check back here every day for updates. We will work to get them on the site by 9 Pm each day of the hearings.

 

Click to contact the Webmaster

Copyright © 2002 Woodlands Coalition for Responsible Energy, Inc.

Back Home Next